Saturday, 9 September 2017

Week 21: Getting There Part 3

Week 21 and we've got floors....so loving our Heartwood Eucalypt floor.... a lot has been done this week and we're so happy... The photos is not doing justice as it is showing sort of brown but in real life it has a combination of a tinge of light grey and a touch of lightest brown and dark shade of grey - a great combination and compliments our grey walls ...
Enjoy looking at them as much as I love staring at it ....






Thanks for dropping by and see you in the next post.


Thursday, 7 September 2017

Week 21: Getting There Part 2

Almost five months since we started our build, we see things coming along ... we can smell PCI (Practical Completion Inspection) ... Week 21 and this is what we have ... door fixtures done ...electrical fittings done including all light battens, ducted rangehood, power points (loving my special grey power point in my back splash), conduits, alarm system, gas points inside and out and of course we have heat and lights in all bathrooms ... main floor tiles (which I am so excited about) is about to start tomorrow --- can't wait to see how our chosen floor tiles would look like in all our area... I think  we are now allowed to slowly get excited

Loved the grey power point that I ordered

Kitchen coming along now

Door fixtures all made - door and built in robe

We have heat and light

Waiting for the toilet




Light batten done

Power points in the media/theatre room

Power points in the media/theatre room

Ducted rangehood installed

Ducted rangehood installed


My much awaited wood look floor tiles are here yiipeee

My much awaited wood look floor tiles are here yiipeee

Walk in robe hanging thingy done

We have heat and light in our ensuite

Where's my toilet lol

Alarm system up

Hot water control done

Power point for our masters done

Walk in wardrobe

Alarm set

Motion detector alarm set


Motion detector alarm set

Motion detector alarm set

Built in wardrobe done

You can never have enough power point, data point and telephone point lol

With alot of gadgets in the kitchen, I opted for as much power point that I can have lol

Gas point and electricity power point outside

Pillar light ready to put in




Blinkers for outside alarm

Thank you for dropping by and see you in our next post :)


Monday, 4 September 2017

Week 21: Getting there Part 1

We just cant contain our excitement from what we've seen today as we snuck in to check what has been made.  True to their words (from the email) things are coming along well ... Let the picture paint you what we have seen and the source of our excitement ....

Image may contain: text

We've got water ... kitchen taps and purifier installed

Main bathroom taps in

Bath in and being weight by water

Main bath taps and shower in

Air conditioning vents put in place in the dining area 

Air conditioning vents put in place in the kitchen area

Laundry has taps and washing machine ready

Ensuite has the taps too

Ensuite shower heads in

Air conditioning vents in the theatre room

Under the sink our plumbing are all good and purifier (hidden at the back of the white pipes) has been installed

Air condition vent in the hallway going to the rooms installed

Aircon vent in one of the kid's room all done

Gas pipe for our heater done.

Thanks for dropping by and see you in the next post.